Blue areas, and the orange trails, are projects that will be constructed during Phase 1 of the park makeover. Yellow areas are projects to be completed in later phases. The pink area will be the future site of the BMX arena, which will be getting a concept sketch done during Phase 1. Image courtesy of the city of Bonney Lake.

Designer given the go-ahead to begin on Allan Yorke Park

Last week, the city of Bonney Lake signed the first of what may be several design contracts with Bruce Dees & Associates for the Allan Yorke Park makeover. The design contract was signed Feb. 7 and will cost the city $286,052 through 2018.

Last week, the city of Bonney Lake signed the first of what may be several design contracts with Bruce Dees & Associates for the Allan Yorke Park makeover.

For the last several months, ever since the City Council approved the park’s master plan last September, council members seemed to have trouble agreeing what Phase 1 would be.

They came to a decision on Jan. 17 to start Phase 1 of the Alan Yorke makeover with a new artificial turf field, a new parking lot and several trails in the south and south-eastern ends of the park.

The plan also includes the design of a BMX track in the same area.

The design contract was signed Feb. 7 and will cost the city $286,052 through 2018.

Special Project Manager Gary Leaf said the dollar amount for the Phase 1 design is a little bit more than estimated, because the artificial turf field, the parking lot and a restroom and concession stand were added to Phase 1 after originally being in the master plan’s Phase 2.

Leaf has said the price of these projects haven’t changed from what they are in the master plan, and that any changes in estimated price comes from moving projects between phases.

The cost of the contract with Bruce Dees & Associates does not include the cost of construction, which is estimated to being the cost up to approximately $3.39 million.

A rough timeline for projects was provided by the designer with the contract.

Bruce Dees & Associates plan to be working on the schematic design and permitting of the project for the rest of the month through the end of June.

The design development process is expected to start around March and end around May, with construction documents then being prepared from May to the end of June.

From there, the designer plans for the city to go out for bid for construction for a month, have the park under construction for four to five months and then take an additional month for the project closeout.

These dates are yet to be determined, because bidding and construction will only follow after all the permits are issued.

Leaf said the designer’s timeline may be too ambitious, and expects designing, permitting and bidding to be completed in 2017, and barring any significant permit issues, start construction by the end of the year and finish in 2018.

The BMX track is not a part of this process, and will only be going through a concept design. The schematic design, permitting, bidding and construction of the BMX area will happen in a later phase.

Leaf said the concept design may cost an additional $25,000 as the city and developer continue to get more input from potential users.

PARKING LOT NOT NEW BOAT TRAILER PARKING

It was previously reported that the new parking lot being built would replace the old gravel boat trailer parking lot, which lies where the new artificial turf field will be installed.

Leaf clarified this development with Bruce Dees, and the parking lot being installed with the field will be mainly for field users and not for boat trailer parking.

“The boat trailers will need to either use this new parking around the ballfield or the old gravel lot next to Ballfield 4 (where the boat trailers used to park) until the new parking area is complete,” Leaf wrote in an email. “Adding the new boat trailer parking lot would have raised the construction cost of this package too much, and we would have had to remove the trails which are popular with the general public or some of the ballfield components (i.e. lighting).”

SLIDES REMOVED FROM ALLAN YORKE

Unrelated to the Allan Yorke Park construction project, the metal slides at Allan Yorke and Cedar View Park were removed at the end of January.

According to Leaf, the manufacturer Play World issued a recall after welds failed on seven out of a total of 1,500 slides.

There was one injury – not in the city – so Play World is re-engineering the slides without welds, Leaf said.

Until the slides are replaced, parents and kids will notice a factory barrier has been installed where the slides used to be.

It is expected the replacement slides will be installed before summer at no cost to the city.

More in News

New utility included in Enumclaw budget; final vote set for Nov. 27

Significant progress has been made on crafting a 2018 Enumclaw budget, a document that could forever change the way the city collects and disperses certain funds. The plan now under way would see creation of a stormwater utility probably by August of the coming year.

Proposed recycling center sparks environmental fears

A proposed material processing facility outside of Enumclaw has some local conservationists worried about how it may affect the Green River and other natural environments. “The location of this, next to this natural area, just is not right. It doesn’t make sense to us at all, for a variety of reasons,” said Bernie McKinney, president of the Green River Coalition, a non-profit preservationist group.

Mobile Impaired Driving Unit hitting the streets this holiday weekend

The MIDU is a self-contained 36 foot motorhome that has been retrofitted as a mobile DUI processing center and incident command post.

Two Enumclaw volunteers honored for work at library

Two members of the Enumclaw Friends of the Library were honored during the recent Friends’ Day, an annual celebration of King County Library System volunteers.

Abigail Hill, 19, is crowned Miss Washington by the 2017 title winner, Alex Carlson-Helo. Photo courtesy Jerry and Lois Photography
Local Miss Washington prepares for national stage

That’s right — Enumclaw is competing in Miss U.S.A. Abigail Hill, the city’s newest star, was recently crowned Miss Washington , clearing the way for her to compete nationally in the spring.

Beyond the Borders now travels from Sumner to Bonney Lake

Come December, it’ll be easier for youth, seniors, people with disabilities or low-income to travel between Sumner and Bonney Lake.

Early start to Crystal ski season

The outdoor season has officially greeted those heading uphill, with snow deep enough to enjoy.

Suspect faces possible ‘third strike’ after alleged car chase, kidnapping

A suspect with a long criminal history finds himself in “third strike” jeopardy, the result of an alleged robbery in Enumclaw and ensuing car chase out of town.

Why now is a good time for a flu shot | Public Health Insider

With the holidays drawing near, many of us look forward to travel or seeing family and friends. And just as our schedules get busier, it’s also the time of year when the flu starts to circulate. We turned to Libby Page, manager of our immunizations program, to get the scoop on flu vaccine.

Election 2017: Change in Enumclaw; Buckley mayor race close

The 2017 general election is over, and although the results are still two weeks from being certified, many candidates are in the clear to take up their elected positions come winter.

Get your fill of winter activities on Mount Rainier

Mount Rainier’s landscape undergoes a dramatic transformation in winter.